8 ft joists, Southern pine
- Double 2x10
- 9' 0"
- Triple 2x10
- 11' 2"
JoyOne factory · deck takeoff
The beam span is the post spacing, so this page answers both: the longest span the table allows for your beam under your joist span, and how many posts that puts under your deck.
9' 2" between posts
Triple 2x10 · 12' 0" joists
Southern pine · Triple 2x10 · 12' 0" joists
9' 2"between posts
| Assembly | 6 ft | 8 ft | 10 ft | 12 ft | 14 ft | 16 ft | 18 ft | |
|---|---|---|---|---|---|---|---|---|
| Double 2x6 | 6′ 11″ | 5′ 11″ | 5′ 4″ | 4′ 10″ | 4′ 6″ | 4′ 3″ | 4′ 0″ | |
| Double 2x8 | 8′ 9″ | 7′ 7″ | 6′ 9″ | 6′ 2″ | 5′ 9″ | 5′ 4″ | 5′ 0″ | |
| Double 2x10 | 10′ 4″ | 9′ 0″ | 8′ 0″ | 7′ 4″ | 6′ 9″ | 6′ 4″ | 6′ 0″ | |
| Double 2x12 | 12′ 2″ | 10′ 7″ | 9′ 5″ | 8′ 7″ | 8′ 0″ | 7′ 5″ | 7′ 0″ | |
| Triple 2x6 | 8′ 6″ | 7′ 5″ | 6′ 8″ | 6′ 1″ | 5′ 8″ | 5′ 3″ | 4′ 11″ | |
| Triple 2x8 | 10′ 11″ | 9′ 6″ | 8′ 6″ | 7′ 9″ | 7′ 2″ | 6′ 8″ | 6′ 4″ | |
| Triple 2x10 | 13′ 0″ | 11′ 2″ | 10′ 0″ | 9′ 2″ | 8′ 6″ | 7′ 11″ | 7′ 6″ | |
| Triple 2x12 | 15′ 3″ | 13′ 3″ | 11′ 10″ | 10′ 9″ | 10′ 0″ | 9′ 4″ | 8′ 10″ |
Every number below comes from the same engine that runs in the browser, at build time, so the examples cannot drift from the calculator above.
A joist attached to a ledger at the house and bearing on a beam at the other end delivers half its load to each. So the beam sees the joist reaction, and the beam table is indexed by the joist span rather than by the deck area: double the joist span and the beam has to span roughly half as far for the same size. That is why the columns run 6 to 18 ft and why reading the wrong column is the most expensive mistake on this page.
The table also assumes a beam supporting a single span of joists, with or without cantilevers, in No. 2 grade with the wet service factor, at 40 psf live and 10 psf dead. It assumes the beam is one assembly fastened with two rows of 10d nails at 16 in on centre along each edge — a built-up beam that is nailed properly, not a pair of boards with a few screws in the middle.
If your deck has a beam under the middle with joists cantilevering past it on both sides, the table still applies to the joist span you type, but the joist span is now measured from the ledger to the beam and the cantilever is separate. If the deck has two beams, each carries a share and each gets its own line; do not read the table for the sum.
The beam table’s footnote and the section text both require the beam depth to be at least the joist depth where the joists hang from the side of the beam. A double 2x8 beam under 2x10 joists is not a smaller version of the right detail; it is a detail that cannot be built flush, and the hanger will not have the nailing it needs. If the beam is shallower than the joists, the joists have to bear on top of it, which changes the whole section height.
This is where doubling and tripling stops being a preference. Going from a double to a triple adds 1 1/2 in of width, which buys roughly 15% more span, and it is often the cheaper move compared to going up a size in depth because it keeps every joist in the deck the size it already is. The calculator prefers the shallowest assembly that reaches your post spacing, so it will offer a triple before it offers a deeper double.
A built-up beam also has to be continuous where it matters. Two 16 ft boards nailed into a 20 ft beam with the joint in the middle of a span is a hinge, not a beam: the plies must be staggered over the posts, and the joint has to land where a post can carry it. No table cell accounts for a badly placed splice, so treat the length as a second constraint after the span.
The maximum span in the table is the maximum distance between post centrelines, and the post count follows from dividing the deck length by it. A 16 ft deck with a 9 ft 2 in beam span divides into two bays of 8 ft, so three posts. A 20 ft deck with the same beam divides into three bays of 6 ft 8 in, so four posts. Dividing equally rather than stepping the maximum is what keeps the joist layout and the beam splice points lined up.
The posts themselves have their own table, R507.4, which limits post height by tributary area: a 4x4 is allowed less than a 6x6, and both are limited to 14 ft. A 96 sq ft tributary at 40 psf live load is past the 80 sq ft row of Table R507.4, where a Southern pine 4x4 is allowed 8 ft 0 in of height and a 6x6 the full 14 ft. That is a different question from the beam span, and confusing the two is how a deck ends up with a post that is too small for the load its beam delivers.
The beam also cantilevers past the end posts, up to a quarter of the actual beam span. On a deck where the beam runs past the last post to the rim, that overhang is doing work: it carries the corner of the deck, and it is limited more tightly than the posts are. If the layout needs a longer overhang than a quarter span, the honest fix is another post.
The beam tables stop at an 18 ft effective joist span, and the prescriptive path stops at an 18 ft joist span for footing design too. Past that the answer is an engineered beam: an LVL, a glulam, or a steel member sized by someone who can run the numbers. This calculator will not print a number past the last column, because a plausible-looking number there is worse than no answer.
The same applies when nothing in the table reaches the post spacing you want. A 16 ft span between posts under 12 ft joists is beyond every built-up 2x assembly in the table in every species, and the calculator says so instead of quietly printing the largest cell. The fix is a mid-span post, a steel beam, or a shorter deck — in that order of cost.
One more limit: the numbers assume the beam is loaded from one side. A beam with joists hanging from both faces carries twice the load for the same span and needs to be checked as such. If your beam sits in the middle of a wide deck with joists on both sides, this page is not the page you need; the joist span is the full width and the beam is carrying half of it from each side.
What the beam answer depends on
The post spacing you end up with is the first half of the footing calculation, because a post carries the deck between it and its neighbours. Multiply the spacing by the joist span and you have the tributary area: 8 ft × 12 ft = 96 sq ft. That is the number Table R507.3.1 is indexed by, and it is why a deck with wide post spacing needs bigger footings even though nothing about the posts themselves changed.
The footing page takes that area and the soil bearing value and returns a diameter, then multiplies by the depth to give cubic feet and bags. Working backwards from a bag count you already like is not a thing this site will help with, because the order is load, then bearing, then size, then concrete — and doing it in that order is what makes the answer checkable.
Finally, the beam span and the post spacing belong on the drawing before a single hole is dug. Set the posts, then the beam, then the joists: the reverse order is how a deck gets built to a beam that does not fit the posts that were already poured. The home page draws the plan from the same numbers these two pages compute, so the three views cannot disagree.
In Southern pine under 10 ft joists, 8 ft 0 in; under 12 ft joists, 7 ft 4 in; under 16 ft joists, 6 ft 4 in. IRC 2021 Table R507.5(1). A triple 2x10 in the same species reaches 10 ft 0 in, 9 ft 2 in and 7 ft 11 in for the same joist spans.
It depends on the beam. With a triple 2x10 in Southern pine under 12 ft joists the beam spans 9 ft 2 in, so 16 ft divides into two bays of 8 ft and three posts. With a double 2x10 the beam spans 7 ft 4 in, so the same deck needs three bays of 5 ft 4 in and four posts.
Not at mid-span. The plies must be staggered and any joint must land over a post, because a joint between supports is a hinge and the table’s capacity assumes a continuous member. Order the beam in one length where you can, and where you cannot, plan the splice over the middle post.
Because the joists deliver their load to the beam, so the beam’s load per foot is proportional to the joist span, not to the deck’s plan area. Doubling the joist span doubles the load on every foot of beam, which is why a longer joist span drops the beam to a shorter column of spans.
It has to be at least as deep as the joists where the joists hang from its side. That is a condition of the table, not a preference: a shallower beam cannot take a flush hanger with the required nailing. Either go deeper, or set the joists on top of the beam and accept the extra height.
| Value | As used here | Basis | Source |
|---|---|---|---|
| Dressed size of 5/4x6 decking | 1 in × 5 1/2 in | Surfaced size, not nominal. Every board count on this site divides by 5.5 in, never by 6 in. | ALSC, American Softwood Lumber Standard PS 20 |
| Dressed size of 2x8 / 2x10 / 2x12 framing | 1 1/2 × 7 1/4 in / 1 1/2 × 9 1/4 in / 1 1/2 × 11 1/4 in | Surfaced size. The section drawing is scaled from these, not from the nominal numbers. | ALSC, American Softwood Lumber Standard PS 20 |
| Maximum joist span, Southern pine 2x8 at 16 in on centre | 11 ft 10 in | Table R507.6 cell. The default 12 ft deck therefore cannot use a 2x8 at 16 in. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Maximum joist span, Douglas fir-larch / hem-fir / SPF 2x10 at 12 in on centre | 15 ft 8 in | Table R507.6 cell, one species group lower than Southern pine in every size. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Maximum joist span, redwood / cedars / ponderosa / red pine 2x12 at 24 in on centre | 12 ft 4 in | Table R507.6 cell; the same size in Southern pine reaches 13 ft 6 in at that spacing. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Beam span, Southern pine double 2x10 under 12 ft joists | 7 ft 4 in | Table R507.5(1) cell, which is also the maximum post spacing for that beam. | ICC, 2021 IRC Table R507.5(1) — deck beam spans, 40 psf live load |
| Beam span, Douglas fir-larch / hem-fir / SPF triple 2x8 under 10 ft joists | 7 ft 11 in | Table R507.5(1) cell. Cantilever at each end is capped at a quarter of the span. | ICC, 2021 IRC Table R507.5(1) — deck beam spans, 40 psf live load |
| Minimum footing, 48 sq ft tributary area on 2,000 psf soil | 14 in round / 12 in square, 6 in thick | Table R507.3.1 row for 40 psf live load. A 2,500 psf soil is read from the 2,000 psf column, never the 3,000 one. | ICC, 2021 IRC Table R507.3.1 — minimum footing size for decks |
| Design live and dead load on a deck | 40 psf live + 10 psf dead | The load case the deck tables are tabulated for; the floor live load table (Table R301.5) sets the 40 psf for decks. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Joist cantilever limit | Lesser of the tabulated value and a quarter of the joist span | Section R507.6 text, not the table: the number in the table is a cap, not a target. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Maximum joist spacing for 1 1/4-inch wood decking | 12 in single span / 16 in multiple span, 8 in and 12 in at 45° | Table R507.7. A board on two joists is single span; on three or more it is multiple span. | ICC, 2021 IRC Table R507.7 — maximum joist spacing for wood decking |
| Bags of concrete per cubic foot | 50 lb fast-setting = 0.375 cu ft; 80 lb concrete mix = 0.60 cu ft | The manufacturers’ own yields: the same hole takes 11 bags of one and 7 of the other. | QUIKRETE Fast-Setting Concrete Mix, data sheet 1004-50 |
| Deck stain coverage | 250–600 sq ft per gallon | A product page, not a code: coverage depends on the wood and the coat. Editable in the form. | Cabot Australian Timber Oil, product page |
| Feet to metres | 1 ft = 0.3048 m exactly | The international foot, so the metric column is a conversion and not a second measurement. | NIST SP 811, Guide for the Use of the SI |
These are estimating tools, not a structural design. Spans are transcribed from the 2021 IRC prescriptive tables for No. 2 grade at 40 psf live and 10 psf dead load, and they only apply to a deck that matches those assumptions: an attached ledger, a built-up beam, posts on footings below the frost line, and the fasteners and connections the code requires. Your local building department, the permit drawings and a licensed engineer decide what is allowed on your site.