40 sq ft on 2,000 psf
- Footing
- 14 in round, 3' 6" deep
- Concrete
- 3.74 cu ft · 10 bags
JoyOne factory · deck takeoff
Give it the area one post carries and the soil under it. The answer is the footing size the load needs, the size the code table requires, whichever is larger, and the concrete that fills it.
17 in footing
2,400 lb · 5.52 cu ft · 15 bags
48 sq ft tributary · 2,000 psf soil · the table governs
17 indiameter × 3' 6" deep
| Bag | Bags | At your price |
|---|---|---|
| 50 lb fast-setting (0.375 cu ft) | 15 | $112.50 |
| 60 lb fast-setting (0.45 cu ft) | 13 | $97.50 |
| 40 lb concrete mix (0.30 cu ft) | 19 | $142.50 |
| 60 lb concrete mix (0.45 cu ft) | 13 | $97.50 |
| 80 lb concrete mix (0.60 cu ft) | 10 | $75.00 |
| Trib. area | 1,500 | 2,000 | 3,000+ | Thick |
|---|---|---|---|---|
| 20 | 12″ | 9″ | 8″ | 6″ |
| 40 | 16″ | 14″ | 12″ | 6″ |
| 60 | 19″ | 17″ | 14″ | 6″ |
| 80 | 22″ | 19″ | 16″ | 7″ |
| 100 | 25″ | 21″ | 17″ | 8″ |
| 120 | 27″ | 23″ | 19″ | 9″ |
| 140 | 29″ | 25″ | 21″ | 10″ |
| 160 | 31″ | 27″ | 22″ | 11″ |
Every number below comes from the same engine that runs in the browser, at build time, so the examples cannot drift from the calculator above.
A footing carries the deck surface between it and the next post, and Table R507.3.1 is indexed by exactly that: the square feet of deck a post supports. For a post in the middle of a run it is the post spacing times the joist span; for a post at the end of a run it is half of that in one direction, which is why corner footings are usually smaller and why a deck with three posts does not have three equal footings.
Take the default 16 × 12 deck with posts at 8 ft: the middle post carries 8 ft × 12 ft = 96 sq ft, which is 4,800 lb of design load. The end posts carry half of that, 48 sq ft and 2,400 lb. Two different footings under one beam is normal, and sizing all of them for the biggest one is a cheap way to avoid getting it wrong.
The arithmetic and the table should agree, and they do closely: 4,800 lb on 2,000 psf soil needs 2.4 sq ft, which is a 21 in circle, and the table’s 100 sq ft row gives 21 in round. Where they disagree the table wins, because it is the code minimum and it includes effects the simple division does not. The calculator prints both so you can see which one set the answer.
The table has three bearing columns: 1,500, 2,000, and 3,000 psf and above. Most undisturbed soil is assumed to be at least 1,500 psf, which is the value the code uses when nobody has tested the ground; a building official can require a soils investigation when weaker material is suspected. If you have a geotechnical report, use its number; if you do not, 1,500 is the honest default.
A soil that sits between columns — 2,500 psf, say — must be read from the weaker column, not the stronger one. Reading 2,500 from the 3,000 psf column would produce a footing smaller than the load needs, and that failure mode is invisible until the deck settles. This calculator picks the highest tabulated value at or below the soil’s, and it labels the column it used.
What the table does not know: whether the soil is expansive clay, fill, or a slope. Those are the conditions where the number is right and the detail is wrong, and they need a local engineer rather than a denser footing. The code itself says so: where the building official finds questionable soils, bearing has to come from an investigation.
The table gives a diameter and a minimum thickness, and nothing about depth. Depth comes from two rules: footings bear at least 12 in below undisturbed grade, and where the deck attaches to a frost-protected structure the footing has to be protected from frost — in practice, below the frost line your building department publishes. That number ranges from a few inches in the Deep South to more than 5 ft in the northern Plains.
Depth is also where the concrete cost lives, because volume scales with it linearly. A 21 in footing at 36 in is 7.2 cu ft; at 48 in it is 9.6 cu ft, which is 26 bags instead of 19 at 50 lb each. On a deck with three posts that is 21 extra bags, or about 1,000 lb of material — worth checking the frost line before you dig rather than after.
If the depth you type is less than the table’s minimum thickness, the calculator uses the thickness instead, because a 4 in pour under a deck post is a plate, not a footing. The code’s thickness is a plain-concrete minimum; a reinforced footing can be thinner but needs an engineer to say so, and this page will not.
A deck footing is usually one of two things: a buried pad with a post base on top, or a cardboard tube filled to the top so the post sits on a concrete pier. The volume calculation here is the simple one — the full shape times the full depth — which is right for a tube and conservative for a pad, where only the bottom portion is concrete.
Bag counts follow from the manufacturer’s yield, and the yields are not interchangeable: 50 lb of fast-setting mix is 0.375 cu ft, 80 lb of concrete mix is 0.60 cu ft. The same 8.4 cu ft hole is 22 bags of one and 14 of the other, at the same total weight of concrete. Fast-setting earns its place on a post hole because it can be poured dry and watered from the top; concrete mix wants a barrow and a hoe.
Order one extra bag per footing, and do not count on a cylinder being a cylinder. An auger in clay digs 2 in oversize, a root pushes it sideways, and the hole at the bottom is never as clean as the one at the top. The extra bags are cheaper than a second trip, and a half-set post is worse than a spare bag on the pallet.
What sets the footing size
A footing that is the right size with a post that is not attached to it is a post that can slide. R507.3.1 requires the footing to give the post complete bearing, and R507.4.1 requires lateral restraint by a manufactured connector or at least 12 in of post embedment in the concrete or the soil — and it removes the embedment option on expansive or questionable soils. A galvanised post base is the usual answer and it costs less than the concrete it sits on.
Where the footing is within 5 ft of the house foundation, the AWC guide is blunt: it must bear at the same elevation as the house footing, or the new load can push the old wall around. That is a detail to check before the first hole, because a footing poured 2 ft higher than the house’s is a footing that has to be broken out.
And the footing is not the end of the load path: the post has to be sized for its height and tributary area (Table R507.4), the beam for its span, and the joists for theirs. Each of those is on its own page here, with the same rule: the number comes from a table, and the table is linked so you can read the footnote that changes it.
It depends on the deck area the post carries and the soil. For 48 sq ft of deck on 2,000 psf soil, IRC 2021 Table R507.3.1 gives a 17 in round or 15 in square footing, 6 in thick — the table is read down to the next row, which is 60 sq ft. For 96 sq ft on the same soil it is 21 in round or 19 in square, 6 in thick.
At least 12 in below undisturbed grade, and below the frost line where the deck attaches to a frost-protected structure. Frost depth is published by your local building department and ranges from a few inches to more than 5 ft. A deeper footing costs concrete: a 21 in footing at 48 in uses a third more than at 36 in.
A 16 in round footing 36 in deep is 4.19 cu ft, so twelve 50 lb bags of fast-setting mix (0.375 cu ft each) or seven 80 lb bags of concrete mix (0.60 cu ft each). At 42 in deep it is 4.89 cu ft, which is 14 bags or 9 bags.
Only if the tributary area is small. On 2,000 psf soil, a 12 in round footing is the table’s answer at 20 sq ft of deck per post, 16 in at 40 sq ft, and 21 in at 96 sq ft. The footing has to spread the load over enough soil, and a 12 in hole is 3.14 sq ft of bearing area whatever the post above it looks like.
The prescriptive tables are written for plain concrete footings with a minimum thickness, so rebar is not required by the table. A reinforced footing can be thinner, and footings on poor soil or carrying unusual loads are often reinforced, but both are engineered decisions rather than table lookups.
| Value | As used here | Basis | Source |
|---|---|---|---|
| Dressed size of 5/4x6 decking | 1 in × 5 1/2 in | Surfaced size, not nominal. Every board count on this site divides by 5.5 in, never by 6 in. | ALSC, American Softwood Lumber Standard PS 20 |
| Dressed size of 2x8 / 2x10 / 2x12 framing | 1 1/2 × 7 1/4 in / 1 1/2 × 9 1/4 in / 1 1/2 × 11 1/4 in | Surfaced size. The section drawing is scaled from these, not from the nominal numbers. | ALSC, American Softwood Lumber Standard PS 20 |
| Maximum joist span, Southern pine 2x8 at 16 in on centre | 11 ft 10 in | Table R507.6 cell. The default 12 ft deck therefore cannot use a 2x8 at 16 in. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Maximum joist span, Douglas fir-larch / hem-fir / SPF 2x10 at 12 in on centre | 15 ft 8 in | Table R507.6 cell, one species group lower than Southern pine in every size. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Maximum joist span, redwood / cedars / ponderosa / red pine 2x12 at 24 in on centre | 12 ft 4 in | Table R507.6 cell; the same size in Southern pine reaches 13 ft 6 in at that spacing. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Beam span, Southern pine double 2x10 under 12 ft joists | 7 ft 4 in | Table R507.5(1) cell, which is also the maximum post spacing for that beam. | ICC, 2021 IRC Table R507.5(1) — deck beam spans, 40 psf live load |
| Beam span, Douglas fir-larch / hem-fir / SPF triple 2x8 under 10 ft joists | 7 ft 11 in | Table R507.5(1) cell. Cantilever at each end is capped at a quarter of the span. | ICC, 2021 IRC Table R507.5(1) — deck beam spans, 40 psf live load |
| Minimum footing, 48 sq ft tributary area on 2,000 psf soil | 14 in round / 12 in square, 6 in thick | Table R507.3.1 row for 40 psf live load. A 2,500 psf soil is read from the 2,000 psf column, never the 3,000 one. | ICC, 2021 IRC Table R507.3.1 — minimum footing size for decks |
| Design live and dead load on a deck | 40 psf live + 10 psf dead | The load case the deck tables are tabulated for; the floor live load table (Table R301.5) sets the 40 psf for decks. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Joist cantilever limit | Lesser of the tabulated value and a quarter of the joist span | Section R507.6 text, not the table: the number in the table is a cap, not a target. | ICC, 2021 IRC Table R507.6 — deck joist spans |
| Maximum joist spacing for 1 1/4-inch wood decking | 12 in single span / 16 in multiple span, 8 in and 12 in at 45° | Table R507.7. A board on two joists is single span; on three or more it is multiple span. | ICC, 2021 IRC Table R507.7 — maximum joist spacing for wood decking |
| Bags of concrete per cubic foot | 50 lb fast-setting = 0.375 cu ft; 80 lb concrete mix = 0.60 cu ft | The manufacturers’ own yields: the same hole takes 11 bags of one and 7 of the other. | QUIKRETE Fast-Setting Concrete Mix, data sheet 1004-50 |
| Deck stain coverage | 250–600 sq ft per gallon | A product page, not a code: coverage depends on the wood and the coat. Editable in the form. | Cabot Australian Timber Oil, product page |
| Feet to metres | 1 ft = 0.3048 m exactly | The international foot, so the metric column is a conversion and not a second measurement. | NIST SP 811, Guide for the Use of the SI |
These are estimating tools, not a structural design. Spans are transcribed from the 2021 IRC prescriptive tables for No. 2 grade at 40 psf live and 10 psf dead load, and they only apply to a deck that matches those assumptions: an attached ledger, a built-up beam, posts on footings below the frost line, and the fasteners and connections the code requires. Your local building department, the permit drawings and a licensed engineer decide what is allowed on your site.